A sage-and-white cottage exterior over restored wood siding, rebuilt window trim and porch, one shallow well on the lot to irrigate both houses, and board and batten inside.
The 1908 yellow house at 910 W Anderson is getting a proper wood-siding restoration and a cottage makeover; a shared irrigation well will serve it and 922 W Anderson.
| Item | Detail |
|---|---|
| Parcels | 910 W Anderson (1908 yellow house), empty lot, 922 W Anderson; all owned |
| Walls | Painted wood clapboard nailed straight to studs; no sheathing or housewrap |
| Insulation | Blown in through drilled holes; raised plugs remain in the siding |
| Foundation | Cement; soil has been pulled back from the wall |
| Moisture | Dry climate; wood was dry when the vinyl came off |
| Termites | Old damage found; looks inactive and possibly treated before |
| Vinyl removal damage | Hundreds of nail holes, split butt joints, hacked window caps, water table chopped at the base |
The goal is sound and sealed, not smooth: keep the laps open, seal every hole in the board faces, and keep wood well clear of the soil.
| What | Filler |
|---|---|
| Small nail holes, up to ⅛" | Exterior-rated filler or paintable urethane-acrylic caulk |
| Holes ¼" and up, gouges | Two-part epoxy (WoodEpox type); Bondo only for small holes in stable wood |
| Stable splits and checks over 1/16" | Epoxy, with consolidant first if the wood is soft |
| Cracks that move with the weather | Paintable urethane-acrylic caulk |
| Insulation plugs | Replace with wood plugs set flush in epoxy |
Keep the original double-hung sash-cord windows and rebuild the trim to one consistent pattern: head casing plus a separate cap.
The look is sage green siding with white trim and a dark door. One protective coat goes on now in the final colour, then a second coat after the repairs.
| Tool | Choice | Notes |
|---|---|---|
| Siding sander | Festool Rotex RO 125, used about $300 on eBay (asked seller for a video and offered $280 shipped) | Cheaper option: reconditioned Bosch GET75-6N at about $160 |
| Finishing sander | Festool ETS 125, used about $155 | Good for trim, not for stripping |
| Dust | Shop vac with HEPA cartridge and cyclone separator, about $60–120 | A true HEPA extractor (DeWalt DWV010/012, Bosch VAC090AH) is better for lead |
| Stripping | Infrared or heat stripper for thick paint | Less lead dust than sanding |
| Joinery | Festool Domino, planer | Already owned |
Cover the existing paneling (cheap 4x8 sheets, some deterioration, unevenness mostly at the sheet seams) with 1/4" hardboard, then add vertical board and batten with crown, per the living-room rendering; replace window and door casings with new trim. All trim in primed finger-jointed pine (MDF dents and chips too easily). Main risks: moisture damage along the floor line, uneven seams telegraphing through, trim depth, heater clearances, and lead paint.
Drill one shallow sand well, about 40–50 ft, on the empty lot between 922 and 910. Use it for irrigation first and keep city water in both houses for now.
| Well | Distance | Depth | Water at | Material | Yield |
|---|---|---|---|---|---|
| Latta #13625 | ~0.5 mi S | 45 ft | 18 ft | Sand at 18–27 ft over shale | 12 gpm |
| Burton #13626 | ~1.0 mi SSW | 40 ft | 15 ft | Sand from 3–40 ft | 15 gpm |
| Benedict #208531 | ~1.2 mi NE | 55 ft | 21 ft | Sand, coarse at 45–55 ft | 45 gpm |
| James #176570 | ~1.5 mi NE | 45 ft | 22 ft | Wet sand at 20–32 ft over clay | 10 gpm |
| City of Waurika #26433 | ~1.9 mi NW | 52 ft | 12 ft | Not logged (1954) | 79 gpm |
| Hunter #92334 | ~2.0 mi E | 105 ft | 20 ft | Water sands at 22–35 and 80–105 ft | 25 gpm |
Deeper wells farther out went into red clay and made 1.5–8 gpm. None of the records include water quality.
| OSU turf rating | Total salts (mg/L) | SAR (sodium) |
|---|---|---|
| Good | 320–960 | 1–2 |
| Fair (manageable) | 960–1,920 | 2–4 |
| Poor | 1,920–3,200 | 4–8 |
| Unacceptable | over 3,840 | over 15 |
| Item | Estimate (100 ft) | At about 45 ft |
|---|---|---|
| Drilling at $45/ft | $4,500 | about $2,025 |
| Pump, tank and fittings | $3,000 | $3,000 |
| Total without well house | $7,500 | about $5,025 |
| Well house option | +$3,000 | skip it; use the pitless setup |
A dry hole is $20/ft. The $500 travel fee applies only over 50 miles.